Tag Archives: No easement

Tribe: False Report on Easement Issued in DAPL

DAPL Drill Pad Update DEC 9 2017-01-02

DAPL Drill Pad Update DEC 9 2017-01-02

Misinformation spread Tuesday about an easement being granted for the final section of the Dakota Access Pipeline. No easement has been approved.

 | Seattle Times Jan 31 2017

A misinformation wildfire lit up social media Tuesday night about the Dakota Access Pipeline (DAPL).

The confusion arose after two congressmen issued news releases late in the day declaring they had been notified the U.S. Army Corps of Engineers has been directed to issue an easement by the acting secretary of the army to complete the pipeline. However, no easement has yet been issued.

The easement is needed by Energy Transfer Partners to complete the last section of the pipeline by drilling under the Missouri River.

The Standing Rock Sioux Tribe issued a statement Tuesday evening intended to calm opponents of the controversial pipeline, reiterating its vow to challenge any easement, if it is issued, in court, and insist on completion of a long-term environmental review of the pipeline project now under way.

Jan Hasselman, attorney for the Standing Rock Sioux, also confirmed no easement has been granted.

“People are jumping the gun,” Hasselman said. He said, however, he expected the easement would be issued soon, probably next week.

Originally published January 31, 2017 at 7:19 pm

Source: Seattle Times